Vietranstimex Completed Transportation and Installation of 02 steel bridges for Mai Dich Interchange

01/10/2024
On December 10th, 2023, Vietranstimex completed the transportation and installation of two steel bridges of Mai Dich Interchange, which is combined of 8 pier-heads and 10 spans each bridge, where the largest piece is 26.5m x 5.5m x 1.3m and weighs 76 tons.

The transportation began on September 20th, 2023. Up to now, the entire installation works has been completed and prepared for handover to the project Investor to do the next work.

Since the project location is located at an intersection which is a busy traffic center of Hanoi City, the installation work is carried out mainly at night in order not to affect traffic at the interchange. Understanding the difficulties caused by limited construction conditions, the Vietranstimex team participating in construction at the project is always determined to uphold the sense of responsibility and strive to quickly complete the project, ensure safety and schedule and soon puts the project into operation.

Congratulations to Vietranstimex team on completing the job successfully! The success of the project will enrich achievements and experience, encourage the efforts of the team on our next journey.