Vietranstimex Has Transported And Installed Span And Pier-Head For Mai Dich Bridge Project

11/29/2023

Continuing the success of projects on steel structure transportation and installation such as Binh Loi Bridge (HCMC), Hoang Van Thu Bridge (Hai Phong), ... and most recently Phat Tich Bridge - Dai Dong Thanh (Bac Ninh), Vietranstimex continues to participate in the transportation and installation of Spans and Cross-head of 26m x 5.5m x 1.6m long, weighing 69 tons of the Mai Dich Bridge Construction Project, Hanoi.

In the scope of work of the project, the main duties consist of:
Transport the entire structures from the processing factories to the construction site using Semi-trailer (SPT) 14 axles, complete the main structure installation and the painting works.
Install, tighten, check, complete adjustment, and check bolts
Weld stud bolt to the beam at the unwelded positions at the factory
Use the 150-220T Crane to install the span segments and crosshead into position

The transportation began on September 20, 2023, and it is expected that all installation will be completed in December 2023. Up to now, we have completed 13/18 bridge spans, expected to shorten the time to complete the work in this November.

The October nights are chilly, with brisk wind picking up in Hanoi, Vietranstimex members are still working hard on the construction site to bring the project go ahead the progress. Wishing the team will complete the project successfully and ahead of schedule! The success of the project will encourage the efforts of the team on our journey to conquering the next great successes.